Structural Retrofitting Works & Fabrication Works
CLIENT NAME | PROJECT NAME | SCOPE | LOCATION | DURATION |
Globe - Huawei | Globe Vindicator Project | Supply &Fabrication of Various Antenna Mounting Bracket |
SMART NCR Sites | September 2014 |
Globe - Alcatel | Globe Vindicator Project | Supply &Fabrication of Various Antenna Mounting Bracket |
Visayas & Mindanao | September 2014 |
RPN - 9 | Radio Philippines Networks Upgrade Expansion Project | Supply, Fabrication & Installation of 24m Guyed Tower |
Iriga City, Albay, Bicol | August 2014 |
Globe - Huawei | Globe Nemesis Project | Supply &Fabrication of Various Antenna Mounting Bracket |
SMART NCR Sites | April - August 2014 |
Belltel - Ericsson | Belltel Rollout Project | Supply & Fabrication of Various 3L SST Minitowers |
NCR | May - July 2014 |
Smart - Huawei | Smart - Sun 3G PH5 Project | Supply, Fabrication & Installation of Various Antenna Mounting Bracket |
SMART NCR Sites | Nov 2013 - January 2014 |
Globe - Huawei | Globe Nemesis Project | Retrofitting Works of Existing GLOBE Visayas Region Sites |
Visayas Region | Aug 2013 |
Belltel - Filcomserve | SMC Belltel Start Project | Supply, Fabrication, Delivery & Erection of 18m 3L SHD SST |
La Huerta Site | Feb 2013 - March 2013 |
Belltel - Filcomserve | SMC Belltel Start Project | Supply, Fabrication, Delivery & Installation of Various Antenna Mounting Bracket |
NCR Sites | Jan 2013 |
DMPI - Ceragon | DMPI Date Project | Retrofitting Works of Existing Pozzurubio, San Isidro, San Carlos, Urbiztondo & Daet Sites |
Pangasinan & Camarines Sur Sites | Nov 2012 - Jan 2012 |
Wi-Tribe - Nokia Siemens | Wi-Tribe L200 Rollout Project | Supply, Fabrication, Delivery & Installation of Various Antenna Mounting Bracket |
Various Sites | Nov 2012 - Jan 2013 |
Globe - Huawei | Globe LTE Project | Supply, Fabrication & Delivery of 3m flr. Mounted AMB, 3m Parapet Mounted AMB, 3M Rooftop Bipod |
NCR Sites | Jun ? Dec 2012 |
DMPI - Huawei | 2G PH9 Project | Supply, Fabrication, Delivery & Installation of Various AMB |
South Luzon Sites | May - Dec 2012 |
Smart - Huawei | Smart FTK 2G Project | Supply, Fabrication & Delivery of Various Bipods |
Huawei Warehouse | April - Dec 2012 |
Smart - Huawei | Smart FTK 2G Project | Supply, Fabrication & Delivery of Various AMB & Bipods |
Huawei Warehouse | Feb 15 - Dec 2012 |
Smart - Huawei | Smart FTK 2G Project | Supply, Fabrication & Delivery of Sun Shelter |
Huawei Warehouse | Feb 15 - July 15 2012 |
DMPI - Huawei | 3G Phase 3 Project | Supply & Delivery of Cable Ladder & Side Struts |
Huawei Warehouse | Oct. 2010 |
AFP - Ceragon | AFP FCS Modernization Project | Design, Fabrication & Erection of 50m 3Legged Self Supporting Tower |
AFP Camp Lapu-Lapu, Cebu City | Oct - Nov 2010 |
AFP - Ceragon | AFP FCS Modernization | Design, Fabrication & Erection of 35m 3Legged Self Supporting Tower |
AFP Camp Capinpin, Tanay Rizal | Oct - Nov 2010 |
Globe - Huawei | Globe Alterra | Supply & Delivery of Base Pad Template |
Huawei Warehouse | Oct. 2009 |
DMPI - Ceragon | DLARP Upgrade | Retrofitting Works for Existing Mt. Cuyapo Tower Strengthening of Main tower legs. |
Cuyapo, Nueva Ecija | Jun - Jul 2007 |
DMPI - Ceragon | DLARP Upgrade | Fabrication & Installation of additional brackets & Retrofitting Works for Mt. Gonzales |
Mt Gonzales, Tagaytay | May 28 - Jun 4 2007 |
DMPI - Ceragon | DLARP Upgrade | Retrofitting Works for Existing Mt. BanoTower Strengthening of Main Hor. and Diagonal Memb. |
Talumpok, Batangas | May 28 - Jun 7 2007 |
DMPI - Ceragon | DLARP Upgrade | Retrofitting Works of Existing Calampon Tower Strengthening of Main Hor. and Diagonal Memb. |
Sariaya, Quezon | May 22 - Jun 3 2007 |