CLIENT NAME | PROJECT NAME | SCOPE | LOCATION | DURATION |
Smart Communication Inc. | Sun Cellular Mindanao S.I. Project | Various Tower Structural Investigation | Sun Cellular Mindanao Sites | January 2015 |
Huawei Tech Phils | GLOBE VINDICATOR PROJECT | Various Tower Structural Investigation | Luzon | Nov. 2014 |
Alcatel Lucent Phils | GLOBE VINDICATOR PROJECT | Various Tower Structural Investigation | Visayas & Mindanao | Nov. 2014 |
RPN - 9 | Radio Philippines Networks Upgrade Expansion Project | Structural Design and Analysis of 24m Guyed Tower | Iriga City, Albay, Bicol | June 2014 |
Globe Telecom | TURISMO PROJECT | Design Services for Structural, Architectural, Electrical & Mechanical – Rectifier & Battery Rooms |
NCR, NLZN,VIS | Jan 2014 |
Globe Telecom | TYPHOON YOLANDA TEMPO SITE RESTORATION |
Structural Investigation for Temporary | Visayas | Oct. – Dec 2013 |
SLDC - Belltel | SMC BELLTEL START Project | Tower Structural Investigation ? Rooftop Sites |
NCR Area | Dec 2013 |
Belltel - Filcomserve | SMC BELLTEL START Project | Structural Design and Analysis of 18m 3L Super Heavy Duty SST |
La Huerta Site | Jan 2013 |
Belltel - Filcomserve | SMC BELLTEL START Project | Tower Structural Investigation Rooftop Sites |
NCR Sites | Jan – April 2013 |
Globe - Huawei | GLOBE MODERNIZATION PILOT Project | Tower Structural Investigation | NCR, NLZN,SLZN | Aug 2012 – Nov. 2013 |
DMPI - Huawei | DMPI 3G PH4 Project |
Civil Works Survey Civil Works Implementation |
NCR | May 2012 - Jan. 2013 |
DMPI - Huawei | SMART?SUN Co?Locate Project | Survey & Implementation | SLZN | May 2012 - Jan. 2013 |
Globe - Huawei | GLOBE DAVAO MODERNIZATION SUHA Project | Civil works Standard Drawing Preparation including Structural Analysis & Design service of Outdoor Equipment support platform & RRU mounting pole with foundation |
Mindanao | Nov 2011 - Jan 2012 |
Globe - Huawei | GLOBE NEMESIS Project | Standard Drawing Preparation for Modernization ( Greenfield / Rooftop Solution ) |
Nationwide | Dec 2011 - May 2012 |
Globe - Huawei | GLOBE MODERNIZATION | Standard Drawing Preparation for Modernization ( Greenfield / Rooftop Solution ) |
Nationwide | Jan 2012 - Jan 2013 |
Globe - Huawei | GLOBE NEMESIS Project | Tower Retrofit for Survey, Analysis, Strengthening Design |
NCR, NLZN, SLZN | July 2012 |
DMPI - Huawei | DMPI FMC Project | Structural analysis of Various Towers | NCR | Jan – June 2012 |
AFP - Huawei | AFP Fixed Communication Systems | Civil Works / Structural analysis of Various Towers |
NCR, Visayas & Mindanao | Aug 2010- March 201 |
DMPI - Ceragon | DMPI Manila - Cebu Access Backbone | Civil Works / Structural analysis of Various Towers |
NCR & Visayas | Jan - September 2010 |
DMPI - Huawei | 3G Phase 3-A Upgrade Project | Site TE Survey & Civil Works & Structural Analysis |
North Luzon | Jan - May 2010 |
DMPI - Huawei | 3G Phase 3-A Upgrade Project | Civil Works / Structural analysis of Various Towers |
North Luzon | Jan - May 2010 |
Smart Communication Inc. | SPDH Phase 8 | Structural Design Analysis of Various Towers |
NCR & South Luzon | June - Oct 2009 |
DMPI - Huawei | 3G Phase 2-A Upgrade Project | CIVIL WORKS STRUCTURAL ANALYSIS |
NCR | May 08 - April 09 |
Smart Communication Inc. | Smart VisMin Expansion Project | Structural Design and Analysis of Various Towers. |
Visayas & Mindanao Sites | January - May 2008 |
Bayantel - Huawei | Wireless Phase 3-A Upgrade | CIVIL WORKS STRUCTURAL ANALYSIS |
NCR | January - Oct. 2008 |
Nokia - Commtrend | Nokia-Seimens | Design/Analysis of 30,40,50,60m Modular Tower for Nokia-Seimens project. |
Jakarta, Indonesia | June - Oct 2007 |
Scancom - Bosung | Ericsson Scancom | Design/Analysis of 30,40,50,60m Modular Tower for Ericson-Ghana Africa Project |
Ghana, Africa | Feb. 2007 - Mar. 2007 |
DMPI - Ericsson - EFB | Digitel Vismin Expansion Project | Structural Design and Analysis of Various Self-Supporting Relay Tower w/ Foundation |
South Luzon | Nov. 2006 - Jan. 2007 |
DMPI - WTS | Digitel GSM Expansion Project | Structural Design and Analysis of Various Rooftop mounted Pole including immediate support |
North Luzon | Feb. 2007 - Aug. 2007 |
DMPI - Alcatel | Digitel South Luzon Expansion Project | Structural Design and Analysis of Various Tower |
South Luzon | June. 2005 - Aug. 2006 |
DMPI - Ceragon | Digitel Luzon Access Redundancy Project (DLARP) | Structural Design and Analysis of New and Existing Self-Supporting and Guyed Tower |
Luzon | Nov. 2005 - Feb. 2006 |
DMPI - Ceragon | 75 HOPS NCR Transmission | Structural Design & Analysis of Monopole & Rooftop Bipod including immediate support structure. |